Friday, May 9, 2008

For the kids to drink

The new field

The sports field is now complete. THis week they put in the new sod.

Wednesday, April 23, 2008

The Mikvah is very close to done

The Dish Mikvah


The Dish Mikvah is outside the building

The decks are complete

Pouring the pool deck

Thursday, April 10, 2008

Warm floors

Look closely and you can see the Nu-Heat system on the floor which will be under the tiles to keep warm. (they are the lines in the concrete)

Kiddie pool taking shape

Tuesday, March 25, 2008

How tall are you?


The tile around the pool and the height markers are in

The Dish Mikvah

The Tiles are going down

Testing the waters

The Mikvahs have been made waterproof - we hope !

Now they are filled up and check for leaks.

Tuesday, March 11, 2008

The pool walls

Pouring the pool walls with a special spray-on concrete called Gunite




Sunday, March 2, 2008

Pouring the pool bottom

The big pool



The Kiddie Pool


The walls are up


Friday, February 22, 2008

It's looking good!


Tuesday, February 19, 2008

Pool taking shape


Wednesday, February 13, 2008

The pool construction begins



Monday, February 11, 2008

And now onto the pool

With the exterior of the Mikvah and locker room building complete the bulk of the workers have shifted to inside.

This has finally cleared the way for the swimming pool work to begin today.


One complete wall

Tuesday, February 5, 2008

Brick going up

Will post some video of this soon.

Monday, February 4, 2008

Ready to brick


Waterproofing

A special material is applied to the Mikvah pool to waterproof it and to keep the water from leaking out.

Thursday, January 31, 2008

We have a roof !

Monday, January 21, 2008

After the "Snow Storm"

Today they couldn't do much outside work due to the ice. The works continued inside.

You can notice one side of the copper roof already up.



Wednesday, January 16, 2008

Snowing in Alpharetta

Believe it or not - it is snowing in Alpharetta. (Usually happens once in 3 years)

This is a picture of the construction site as the snow began to fall.

Hopefully we can get some nice white pictures tomorrow if the snow keeps on falling.


The "Mock-Up"

Today the mason made a "mock-up" sample of the exterior walls of the building. Once the architect approves then they will begin to brick the building.

Time for some answers

On Friday we had a "meeting of the minds" to get answers for some of the questions that have come up during the last few weeks.

Monday, January 14, 2008

Count the Pickup trucks

This is the south so every one on the job site owns a pickup truck.

Tuesday, January 8, 2008

Black & White

All dressed in white

Today they are also dressing the side walls with TYVEC which is a plastic material to keep out water from the walls. This is a layer which goes on before the bricks.

All dressed in black

Today they are dressing the roof with black felt paper which goes on before the roof material to help keep out the water.

Wednesday, January 2, 2008

The Fire

The workers try to stay warm in the Georgia cold.

The walls go up - Video

Many have been asking for more videos. So here is a nice video of the outside walls going up.

Tuesday, January 1, 2008

Looking like a building now

The outside walls are all covered with plywood and ready for the brick. The roof plywood is being finished this week.



We are back

We were away for a few days and look how much is done!

Sorry for all you bloggers for having to miss the updates.

Tuesday, December 18, 2007

Taking Shape


All the walls are now framed.Next goes the roof. How exciting!

Monday, December 17, 2007

The walls are going up !!!!!!!


Ready to start framing



Now that the slab is in the framing crew is here getting ready to start the walls.

By the end of the week the place should look a lot different. Very exciting.

Thursday, December 13, 2007

The Slab

What it must have felt like building Mikvahs in Russia. :-)

Pouring the slab in the dark

Wednesday, December 12, 2007

Getting ready for concrete




The underground utilities are all in. They have already laid the first layer of rock and are now ready to pour the slab which should happen IY"H tomorrow.

Monday, December 3, 2007

"Rough in"


Today (Monday, 12/3/07) the are roughing in the underground plumbing before they get ready to pour the slab.

Monday, November 26, 2007

Pouring the cement

Thursday, November 22, 2007

The Mikvahs are in !!!


Tuesday, November 20, 2007

The Concrete




Today they poured the concrete for the Mikvah - immersion pool.

Wednesday, November 14, 2007

"The Mikvah Expert"

Two Rabbi's how many opinions?



Today (Wednesday, November 14) the "Mikvah Expert" Rabbi Gershon Grossbaum came to visit the site to make sure that the concrete forms for the Mikvah conform to Halachic standard.

Wednesday, November 7, 2007

What's that?


Today they began lowering specially built forms into the Mikvah hole. This will give them the ability to pour the cement for the Mikvah in the appropriate Halachic way.





Tuesday, November 6, 2007

Our annual raffle





Monday, November 5, 2007

Digging the Mikvah Hole